Standing Rock Telecom Fiber Optic Line
Project Summary
Location Summary:
Section 15, T129N, R89W; Section 17 T129N, R88W; Section 28, T129N R87W
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 1/13/2026 |
| Decision | 1/15/2025 |
Expected Analysis Type:
Categorical Exclusion
Lead Management Unit:
Grand River Ranger District
Project Purpose:
Special use management
Current Status:
Completed
Project Decision Information
Decision Signed Date: 1/15/2025
States:
South Dakota; North Dakota
Counties:
Corson; Sioux
Steve Best
c/o Grand River Ranger District
1005 5th Ave W
Lemmon, South Dakota 57638
701-989-7283
steven.best@usda.gov
Last Updated: 1/15/2026