APS Coconino-Padre 69kV Transmission Line Rebuild
Replacement of aging existing transmission line and poles to allow for safer and more reliable electrical service. The static wire on the transmission line would be replaced with optical ground wire, allowing for fiber optic communication uses.
Project Summary
Location Summary:
Transmission line that runs south of I40 from the Coconino substation, south of the Northern Arizona University in Flagstaff, to the Padre substation, near Twin Arrows Casino
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/2025 (Estimated) |
Decision | 09/2025 (Estimated) |
Implementation | 10/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Coconino National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission; Special Use Authorizations
Current Status:
Developing Proposal
Forests:
Coconino National Forest
Districts:
Flagstaff Ranger District
States:
Arizona
Counties:
Coconino
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Tobias Hutchens
1824 S. Thompson St.
Flagstaff, AZ 86001
928-527-3471
tobias.j.hutchens@usda.gov
Last Updated: 3/26/2025