Ebey Eastside Pine Restoration Project (Ebey Project)
Implementation of the Herger-Feinstein Quincy Library Group Forest Recovery Act, as amended by the Sierra Nevada Forest Plan Amendment FSEIS ROD.
Project Summary
Location Summary:
Eagle Lake Ranger District
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/23/2010 |
| Objection Period Start | 12/15/2010 |
| Decision | 03/2011 (Estimated) |
| Implementation | 05/2011 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Hfra Title I: Threats To Ecosystem Components (Such As Insect Or Disease Epidemics)
Lead Management Unit:
Eagle Lake Ranger District
Notice and Comment Regulation:
218
Project Purpose:
Fuels Management; Forest Products; Vegetation Management (Other Than Forest Products)
Project Activity:
Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements
Current Status:
Completed
Project Decision Information
Ebey Eastside Pine Restoration Project
Decision Signed Date: 03/28/2011
Forests:
Lassen National Forest
Districts:
Eagle Lake Ranger District
States:
California
Counties:
Lassen
Legal Land Description:
T32N, T33N, R6E, R7E
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Terre PearsonRamirez
477-050 Eagle Lake Road
Susanville, CA 96130
(530) 257-4188
tramirez@fs.fed.us
Last Updated: 3/28/2011