Bailey Creek Aquatic Organism Passage (AOP) Project
Two existing culverts on the North & South Forks of Bailey Creek will be replaced with bridges to eliminate barriers to the passage of aquatic organisms and damage to road crossing when rivers are at high stage.
Project Summary
Location Summary:
Lassen NF 17 Road to the west of Lassen Volcanic National Park
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/24/2018 |
Decision | 05/2018 (Estimated) |
Implementation | 08/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hat Creek Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management; Wildlife, Fish, Rare Plants; Watershed Management
Project Activity:
Species Habitat Improvements; Watershed Improvements
Current Status:
Completed
Project Decision Information
Bailey Creek Aquatic Organism Passage (AOP) Project
Decision Signed Date: 05/03/2018
Forests:
Lassen National Forest
Districts:
Hat Creek Ranger District
States:
California
Counties:
Shasta
Legal Land Description:
T31N,R3E,S34
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Shawn Wheelock
43225 E. Hwy. 299
Fall River Mills, CA 96028
530-336-3340
swheelock@fs.fed.us
Last Updated: 5/3/2018