Hat Creek Debris Removal and Stream Bank Stabilization Project
The Hat Creek Debris Removal and Stream Bank Stabilization Project is proposed to stabilize the channel and minimize further sedimentation, protect state and federal infrastructure, and improve visitor safety.
Project Summary
Location Summary:
Hat Creek channel between Cave Campground and Bridge Campground, Township 33N, Range 5E, Sections 8,9,16,21,and 28.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/09/2018 |
| Decision | 03/2018 (Estimated) |
| Implementation | 05/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (19), 36 Cfr 220.6(E)(19)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hat Creek Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management; Recreation Management
Project Activity:
Watershed Improvements
Current Status:
Completed
Project Decision Information
Hat Creek Debris Removal and Stream Bank Stabilization Project
Decision Signed Date: 03/27/2018
Forests:
Lassen National Forest
Districts:
Hat Creek Ranger District
States:
California
Counties:
Shasta
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Shawn Wheelock
43225 E. Hwy. 299
Fall River Mills, CA 96028
530-336-3340
swheelock@fs.fed.us