Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 09/03/2003 |
| Comment Period | 11/02/2005 |
| Decision | 04/2006 (Estimated) |
| Implementation | 07/2006 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
McCloud Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Fuels Management; Forest Products
Project Activity:
Timber Sales (Salvage); Timber Sales (Green)
Project Decision Information
Edson Project
Decision Signed Date: 04/12/2006
Legal Notice Date: 04/16/2006
Forests:
Shasta Trinity National Forest
Districts:
McCloud Ranger District
States:
California
Counties:
Siskiyou
Legal Land Description:
T40N,R1E, MDB&M, Sections 2, 11, 13, 14, 23, 24, 25,26; T41N,R1E, MDB&M, Sections 25, 26,35
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Steve Funk
P.O. Box 1620
McCloud, CA 96057
(530) 964-3770
sfunk@fs.fed.us
Last Updated: 6/28/2010