Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/30/2011 |
Comment Period | 02/2016 (Estimated) |
Decision | 03/2017 (Estimated) |
Implementation | 08/2017 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Big Bar Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Watershed Management
Project Activity:
Road Decommissioning; Road Maintenance; Watershed Improvements
Current Status:
Cancelled
Forests:
Shasta Trinity National Forest
Districts:
Big Bar Ranger District
States:
California
Counties:
Trinity
Legal Land Description:
The watershed is located in T.34N., R.11W., sections 21-29 and 32-36; T.33N., R.11W., sections 1-5, 8-17, 21-28 and 33-36; T.32N., R.11W., sections 1-4, 10-12 and 14; T.33N., R.10W., sections 18, 19 a
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Brad Rust
Star Route 1, Box 10
Big Bar, CA 96010
530-226-2427
brust@fs.fed.us