Lower McCloud Fuels Management Project
Mechanical and prescribed fire fuels reduction within ~12,000 acres in the Lower McCloud and Lower Squaw Valley Creek watersheds.
Project Summary
Location Summary:
Bald Mountain Ridge, Ah-Di-Na, McCloud River, Cabin Creek areas.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/22/2016 |
| Comment Period | 02/05/2021 |
| Objection Period Start | 04/23/2021 |
| Decision | 08/2021 (Estimated) |
| Implementation | 08/2021 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
National Fire Plan - Other
Lead Management Unit:
McCloud Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Fuels Management; Vegetation Management (Other Than Forest Products)
Project Activity:
Fuel Treatments (Non-Activity Fuels)
Current Status:
Completed
Project Decision Information
Lower McCloud Fuels Management Project
Decision Signed Date: 08/04/2021
Forests:
Shasta Trinity National Forest
Districts:
McCloud Ranger District
States:
California
Counties:
Shasta
Legal Land Description:
T37N R2W 5,6; T37N R3W 1-3, 10-12, 14-15, 23; T38N R2W 19, 27-33; T38N R3W 13-15, 22-28, 33-36
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Emelia Barnum
P.O. Box 1620
McCloud, CA 96057
530-926-4511
ebarnum@fs.fed.us
Last Updated: 8/22/2022