Ski Park Road Reauthorization
Wintun Development Corporation has requested reauthorization of their Special Use Permit for the two-lane paved public road that provides for the year-round access to the Mt. Shasta Board and Ski Park. The road segment was constructed with the Park.
Project Summary
Location Summary:
This road segment is the uppermost portion of the Ski Park Highway that connects Highway 89 to the Mt. Shasta Board and Ski Park
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 08/08/2012 |
| Comment Period | 08/08/2012 |
| Decision | 09/2012 (Estimated) |
| Implementation | 09/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (15)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Mt. Shasta Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Mt. Shasta Board and Ski Park Road Special Use Permit Authorization
Decision Signed Date: 09/10/2012
Legal Notice Date: 09/13/2012
Forests:
Shasta Trinity National Forest
Districts:
Mt. Shasta Ranger District
States:
California
Counties:
Siskiyou
Legal Land Description:
NW1/4 section 16, t.40N., R.3W., M.D.B.M.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Stacy Smith
204 West Alma
Mt. Shasta, CA 96067
530-926-4511
slsmith01@fs.fed.us