Bridge Bay Resort Storm Water Filtration System Installation
Authorize installation of storm water filtration system, including a 3 feet deep x 5 feet wide x 36 feet long filtration basin, at Bridge Bay Resort in location where storm water discharges to Shasta Lake from the south boat ramp paved parking lot.
Project Summary
Location Summary:
Shasta Unit of the Whiskeytown-Shasta-Trinity National Recreation Ares. Bridge Bay Resort, 10300 Bridge Bay Road, Redding, CA
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 08/24/2023 |
| Decision | 10/2023 (Estimated) |
| Implementation | 11/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Shasta Lake Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Bridge Bay Resort Storm Water Filtration System Installation
Decision Signed Date: 10/21/2023
Forests:
Shasta Trinity National Forest
Districts:
Shasta Lake Ranger District
States:
California
Counties:
Shasta
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Amber Machado
14250 Holiday Road
Redding, CA 96003
530-510-3015
Amber.Machado@usda.gov
Last Updated: 8/29/2024