Midstate Electric Cooperative Cultus Lake Pole Replacements
This project would authorize Midstate Electric Cooperative to replace two damaged power poles east of Crane Prairie Reservoir to maintain electrical safety and integrity.
Project Summary
Location Summary:
The project location is approximately 1.5 miles east of Crane Prairie Reservoir
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/17/2022 |
| Decision | 04/2022 (Estimated) |
| Implementation | 04/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Bend/Fort Rock Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Midstate Electric Cooperative Cultus Lake Pole Replacements
Decision Signed Date: 04/13/2022
Forests:
Deschutes National Forest
Districts:
Bend/Fort Rock Ranger District
States:
Oregon
Counties:
Deschutes
Legal Land Description:
T20S R8E Sections 26 and 35
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Alicia Bergschneider
63095 Deschutes Market Rd
Bend, OR 97701
541-383-4012
alicia.bergschneider@usda.gov