Noonday Trail Blasting
Blasting of rock outcropping to remove a barrier to motorized trail use.
Project Summary
Location Summary:
Near the confluence of Brice Creek and Champion Creek in the Brice Creek Watershed.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/07/2010 |
Decision | 06/2010 (Estimated) |
Implementation | 09/2010 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Cottage Grove Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Current Status:
Completed
Project Decision Information
Noonday Trail Blasting
Decision Signed Date: 06/03/2010
Forests:
Umpqua National Forest
Districts:
Cottage Grove Ranger District
States:
Oregon
Counties:
Lane
Legal Land Description:
T22S R1E, Sec 23
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Melissa Swain
34963 Shoreview Drive
Cottage Grove, OR 97424
541-767-5015
mbswain@fs.fed.us
Last Updated: 9/14/2010