Calapooya Divide Integrated Project
This project is designed to improve stand health and diversity, improve fire resiliency, provide forest products and maintain/restore meadow habitats.
Project Summary
Location Summary:
Project Area is within the upper portion of the Sharps Creek Watershed.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 12/18/2014 |
| Comment Period | 08/08/2017 |
| Objection Period Start | 03/20/2018 |
| Decision | 07/2019 (Estimated) |
| Implementation | 09/2019 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Cottage Grove Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Forest Products; Fuels Management; Vegetation Management (Other Than Forest Products)
Project Activity:
Forest Vegetation Improvements; Noxious Weed Treatments; Road Maintenance; Timber Sales (Green); Watershed Improvements
Current Status:
Completed
Project Decision Information
Calapooya Divide Integrated Project
Decision Signed Date: 07/12/2019
Forests:
Umpqua National Forest
Districts:
Cottage Grove Ranger District
States:
Oregon
Counties:
Lane
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Elspeth Gustavson
34963 Shoreview Drive
Cottage Grove, OR 97424
541-496-4169
egustavson@fs.fed.us
Last Updated: 7/12/2019