Raco Construction
EA -- Sell the district office in Sault Ste. Marie, close the Moran Work Center, remove the current office building and four outbuildings from the Raco Work Center, and construct a new office building, heavy equipment maintenance building, and fire cache at the Raco Work Center.
Project Summary
Current Status:
Completed
Location Summary:
The Raco work center is north of M-28 and west of Raco; Moran work center is in town of Moran
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/09/2009 |
| Comment Period | 07/09/2009 |
| Decision | 04/2010 (Estimated) |
| Implementation | 06/2010 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
St. Ignace Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Facility Management
Project Activity:
Facility Improvements/Construction
Project Decision Information
Raco Construction
Decision Signed Date: 04/19/2010
Forests:
Hiawatha National Forest
Districts:
Sault Ste. Marie Ranger District; St. Ignace Ranger District
States:
Michigan
Counties:
Chippewa; Mackinac
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Stevan Christiansen
W1900 US 2
St. Ignace, MI 49781
906-643-7900
sjchristiansen@fs.fed.us
Last Updated: 4/26/2010