American Transmission Company Raco Switch
The purpose of this project is for ATC to replace a manual switch along their line with a remotely operated switch. A remotely operated switch provides safer more efficient access to activate and deactivate their telecommunication lines.
Project Summary
Current Status:
Completed
Location Summary:
Access will be from M-28 to Middletown Rd (FS Rd 3081) to the right-of-way. Access will be down the ROW and along Dishpan Rd (FS Rd 3364).
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 12/08/2016 |
| Decision | 04/2017 (Estimated) |
| Implementation | 05/2017 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hiawatha National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
American Transmission Company Raco Switch
Decision Signed Date: 04/11/2017
Forests:
Hiawatha National Forest
Districts:
St. Ignace Ranger District
States:
Michigan
Counties:
Chippewa
Legal Land Description:
T46N R4W Sections 16, 15, 21, 22, 28, 27
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Karina Hawley
820 Rains Drive
Gladstone, MI 49829
906-428-5833
khawley@fs.fed.us
Last Updated: 12/10/2019