Carp Project
Vegetation Management and Recreation proposal
Project Summary
Location Summary:
Proposed activities include vegetation management and a recreation component
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/03/2025 |
Comment Period | 01/04/2025 |
Objection Period Start | 06/2025 (Estimated) |
Decision | 08/2025 (Estimated) |
Implementation | 09/2025 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hiawatha National Forest All Units
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Forest Products
Project Activity:
Timber Sales (Green)
Current Status:
In Progress
Forests:
Hiawatha National Forest
Districts:
Sault Ste. Marie Ranger District; St. Ignace Ranger District
States:
Michigan
Counties:
Chippewa; Mackinac
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Shane Flickinger
820 Rains Drive
Gladstone, MI 49829
906-298-8123
shane.flickinger@usda.gov
Last Updated: 1/6/2025