Carp River Campground Building Removal
Decommission the existing toilet building 96514, including demolition, removal, and restoration of the site.
Project Summary
Current Status:
Completed
Location Summary:
Carp River Campground - T42N, R3W, Sec18 - Between sites 10 and 19
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 12/12/2024 |
| Decision | 03/2025 (Estimated) |
| Implementation | 09/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (22), 36 Cfr 220.6(E)(22)
Special Authority:
Not Applicable / Other
Lead Management Unit:
St. Ignace Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management; Facility Management
Project Activity:
Developed Site Management
Project Decision Information
Carp River Campground Building Removal
Decision Signed Date: 03/14/2025
Forests:
Hiawatha National Forest
Districts:
St. Ignace Ranger District
States:
Michigan
Counties:
Mackinac
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Julia Hall
W1900 US 2
St. Ignace, MI 49781
906-643-7900 ext:132
julia.hall@usda.gov
Last Updated: 3/14/2025