UPPCO Amendment 12 - Bay Furnace Campground Powerline Replacement
This line has reached end of life conditions, has failed beyond repair, and needs replacement as quickly as possible to limit recreational impacts on concessionaire campground hosts, services, and recreators.
Project Summary
Current Status:
Completed
Location Summary:
Bay Furnace Campground
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/30/2025 |
| Decision | 05/2025 (Estimated) |
| Implementation | 05/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Munising Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Facility Improvements/Construction; Special Use Authorizations
Project Decision Information
UPPCO Amendment 12 - Bay Furnace Campground Powerline Replacement
Decision Signed Date: 05/01/2025
Forests:
Hiawatha National Forest
Districts:
Munising Ranger District
States:
Michigan
Counties:
Alger
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Rita Morris
400 E. Munising Ave
Munising, MI 49862
000-000-0000
rita.morris@usda.gov