Upper Peninsula Power Company (UPPCO) Re-issued Special Use Permit for Powerline Corridor
CE -- Renew special use permit for an existing powerline corridor crossing National Forest System land.
Project Summary
Location Summary:
Powerline corridor is found on the Westside and the Eastside of the Hiawatha National Forest
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/23/2009 |
Decision | 07/2009 (Estimated) |
Implementation | 12/2010 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hiawatha National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Upper Peninsula Power Company Re-issued SUP for Powerline Co
Decision Signed Date: 07/27/2009
Forests:
Hiawatha National Forest
Districts:
Hiawatha National Forest All Units
States:
Michigan
Counties:
Alger; Chippewa; Delta; Mackinac; Schoolcraft
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Susan Alexander
820 Rains Drive
Gladstone, MI 49829
906-789-3327
smalexander@fs.fed.us
Last Updated: 4/21/2010