Great Lakes Gas Pipeline Permit Reissuance
CE -- Renewal of Special Use Permit for an existing gas pipeline corridor crossing National Forest System Land
Project Summary
Location Summary:
Gas pipeline corridor is found on the Westside and the Eastside of the Hiawatha National Forest
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/09/2010 |
Decision | 11/2010 (Estimated) |
Implementation | 01/2011 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (15)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hiawatha National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Great Lakes Gas/TransCanada Pipeline Special Use Permit Renewal
Decision Signed Date: 11/10/2010
Forests:
Hiawatha National Forest
Districts:
Rapid River Ranger District; Manistique Ranger District; Sault Ste. Marie Ranger District; St. Ignace Ranger District
States:
Michigan
Counties:
Chippewa; Delta; Mackinac; Schoolcraft
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Susan Alexander
820 Rains Drive
Gladstone, MI 49829
906-789-3327
smalexander@fs.fed.us
Last Updated: 12/27/2010