Cloverland Cooperative Electric Company Powerline Replacement
CE -- Removal of overhead powerline lines and poles and replace with underground line within the existing corridor.
Project Summary
Location Summary:
On the St. Ignace Ranger District
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/14/2011 |
Decision | 11/2011 (Estimated) |
Implementation | 03/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hiawatha National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Cloverland Cooperative Electric Company Powerline Replacement
Decision Signed Date: 11/28/2011
Forests:
Hiawatha National Forest
Districts:
St. Ignace Ranger District
States:
Michigan
Counties:
Mackinac
Legal Land Description:
T42N, R5W, Sections 22 and 27
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Susan Alexander
820 Rains Drive
Gladstone, MI 49829
906-789-3327
smalexander@fs.fed.us
Last Updated: 11/29/2011