Cloverland Electric Cooperative Special Use Permit Amendment
Special Use Permit Amendment for the construction of three new underground lines and the adoption of a new Operation and Maintenance Plan.
Project Summary
Location Summary:
St. Ignace, Sault Ste. Marie, and Manistique Ranger Districts.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/15/2013 |
Comment Period | 07/15/2017 |
Decision | 12/2017 (Estimated) |
Implementation | 12/2017 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hiawatha National Forest All Units
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Cloverland Electric Cooperative Special Use Permit Amendment
Decision Signed Date: 12/13/2017
Forests:
Hiawatha National Forest
Districts:
Manistique Ranger District; Sault Ste. Marie Ranger District; St. Ignace Ranger District
States:
Michigan
Counties:
Chippewa; Delta; Mackinac
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Robert West
820 Rains Drive
Gladstone, MI 49829
906-643-7900
robertwest@fs.fed.us
Last Updated: 12/13/2017