2013-Cloverland Electric Special Use Permit Re-issue
Re-issue Special Use Permit to include: All existing distribution lines and Rights of Way within HNF lands, Electric substations at Eckerman and Raco locations.
Project Summary
Location Summary:
Distribution line Rights of Way located across Eastside of HNF (Mackinac & Chippewa Counties) and a small portion of Manistique Ranger District (Delta County)
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/31/2013 |
Comment Period | 05/31/2013 |
Decision | 11/2013 (Estimated) |
Implementation | 12/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (15)
Special Authority:
Not Applicable / Other
Lead Management Unit:
St. Ignace Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
2013 Cloverland Electric Special Use Permit Re-issue
Decision Signed Date: 11/20/2013
Legal Notice Date: 12/11/2013
Forests:
Hiawatha National Forest
Districts:
Hiawatha National Forest All Units
States:
Michigan
Counties:
Chippewa; Delta; Mackinac
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Bradley Cooper
W1900 US 2
St. Ignace, MI 49781
906-643-7900
bradleylcooper@fs.fed.us
Last Updated: 12/20/2013