Merit Network, Inc. Highway M-28 Buried Fiber Optic Installation
Bury approximately 14 miles of fiber optic cable within the north shoulder of Highway M-28, within the highway right-of-way. The fiber optic cable would extend the entire length of M-28 on the East Zone of the Hiawatha National Forest.
Project Summary
Location Summary:
The north shoulder of Highway M-28, within the highway right-of-way, within the East Zone Hiawatha National Forest Boundary.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/09/2022 |
Decision | 11/2022 (Estimated) |
Implementation | 07/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Sault Ste. Marie Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Merit Network, Inc. Highway M-28 Buried Fiber Optic Installation
Decision Signed Date: 11/11/2022
Forests:
Hiawatha National Forest
Districts:
Sault Ste. Marie Ranger District
States:
Michigan
Counties:
Chippewa
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Daniel Aklufi
W1900 West US-2
St. Ignace, MI 49781
906-428-5827
daniel.aklufi@usda.gov
Last Updated: 7/7/2023