Project Milestones:
| Milestone | Date |
|---|---|
| NEPA Start Date | 7/28/2026 |
| Finding/Decision Date | 7/31/2026 |
Expected Analysis Type:
Categorical Exclusion
Categorical Exclusion:
TVA 22 (18 CFR Appendix A to Subpart C of Part 1318(22))
Lead Management Unit:
Sheyenne Ranger District
Project Purpose:
Recreation management
Project Decision Information
Decision Signed Date: 7/31/2026
States:
North Dakota
Counties:
Ransom; Richland
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Steve Best
c/o Sheyenne Ranger District
1601 Main St.
P.O. Box 946
Lisbon, North Dakota 58054
701-989-7283
steven.best@usda.gov
Last Updated: 7/31/2026