SM Energy's Rocky Top Federal 4-9H Oil Well
SM Energy proposes to construct an oil and gas well, well pad, access road and associated utilities to exercise its right to develop its federal mineral lease.
Project Summary
Location Summary:
Approximately 15 miles northwest of Fairfield, North Dakota
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/31/2015 |
Decision | 02/2016 (Estimated) |
Implementation | 10/2016 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Medora Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations; Road Improvements/Construction
Current Status:
Completed
Project Decision Information
SM Energy's Rocky Top Federal 4-9H Oil Well
Decision Signed Date: 02/25/2016
Forests:
Dakota Prairie Grasslands
Districts:
Medora Ranger District
States:
North Dakota
Counties:
Billings
Legal Land Description:
NWNW Section 9 T144N, R101W
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jason Dekker
99 23rd Avenue W, Suite B
Dickinson, ND 58601-3135
701-227-7821
jdekker@fs.fed.us
Last Updated: 2/26/2016