Goodnight Midstream Midway to Cleetwood Pipeline Project
The Goodnight Midstream Midway to Cleetwood Pipeline Project would consist of installing 0.77 miles (4,050 feet) of 8-inch Star Fiberglass pipeline within a 20-foot right-of-way (4.6 acres) and will be buried to a depth of 60 inches on NFS lands.
Project Summary
Location Summary:
Section 27, Township 152N, Range 97W, 5th PM, McKenzie County, North Dakota
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 10/14/2021 |
| Decision | 11/2021 (Estimated) |
| Implementation | 11/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Oil & Gas - Sec. 390, Energy Policy Act Of 2005 (Sec 390)
Lead Management Unit:
Mckenzie Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Goodnight Midstream Midway to Cleetwood Pipeline Project
Decision Signed Date: 11/17/2021
Forests:
Dakota Prairie Grasslands
Districts:
Mckenzie Ranger District
States:
North Dakota
Counties:
McKenzie
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kim Grotte
1905 Main St. South
Watford City, ND 58854-6705
701-842-2393
kim.grotte@usda.gov
Last Updated: 11/22/2021