McKenzie Electric Cooperative, Inc. Horse Creek East & West New Build
McKenzie Electric Cooperative, Inc. proposes to construct a buried electrical line across National Forest System lands in McKenzie County, North Dakota.
Project Summary
Location Summary:
Sections 26 and 35, T149N, R104W, 5th PM, McKenzie County, North Dakota
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 08/15/2022 |
| Decision | 07/2023 (Estimated) |
| Implementation | 07/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Mckenzie Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
McKenzie Electric Cooperative, Inc. Horse Creek East & West New Build
Decision Signed Date: 07/14/2023
Forests:
Dakota Prairie Grasslands
Districts:
Mckenzie Ranger District
States:
North Dakota
Counties:
McKenzie
Legal Land Description:
Sections 26 and 35, T149N, R104W, 5th PM, McKenzie County, North Dakota
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Stacy Defoe
1905 Main St. South
Watford City, ND 58854-6705
7018428510
Stacy.Defoe@usda.gov