Belfield Fiber Optic Phase 3
Consolidated Enterprises, Inc. is requesting a SUP amendment to include 31 miles of fiber optic line to provide high-speed internet to rural residents and businesses in Southwestern ND.
Project Summary
Location Summary:
Phase 3 consists of 30.9 miles located in several townships of Billings County, North Dak
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/14/2024 |
| Decision | 05/2024 (Estimated) |
| Implementation | 06/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Medora Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Belfield Fiber Optic Phase 3
Decision Signed Date: 05/17/2024
Forests:
Dakota Prairie Grasslands
Districts:
Medora Ranger District
States:
North Dakota
Counties:
Billings; Slope; Stark
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Ian Barr
99 23rd Avenue W, Suite B
Dickinson, ND 58601-3135
000-000-0000
Ian.Barr@usda.gov
Last Updated: 5/21/2024