Barker Gravity Pipeline Special Use Permits
This project will amend an existing master permit for Barker Gravity pipeline to add an access road and issue 1-2 new temporary special use permits for rock wall repairs and siphon replacements within the Barker Gravity Pipeline area.
Project Summary
Location Summary:
These projects will take place within the Barker Gravity Pipeline line system.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 09/06/2024 |
Decision | 05/2025 (Estimated) |
Implementation | 05/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Boulder Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
In Progress
Forests:
Arapaho and Roosevelt National Forests
Districts:
Boulder Ranger District
States:
Colorado
Counties:
Boulder
Legal Land Description:
T1S, R71W, Sec. 6, 9 and T1S, R72W, Sec. 1, 9
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
2140 Yarmouth Avenue
Boulder, CO 80301
303-541-2534
Lauren.Kryszczuk@usda.gov
Last Updated: 4/17/2025