PSCo Van Eden Line Distribution Line Extension Phase 2
PSCo has identified the need to install eight distribution poles. The pole installments will allow PSCo to provide safe and reliable service to a new customer.
Project Summary
Location Summary:
Van Eden Road, at T4S, R73W, Sec. 11
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/14/2024 |
Decision | 09/2024 (Estimated) |
Implementation | 10/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Clear Creek Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
In Progress
Forests:
Arapaho and Roosevelt National Forests
Districts:
Clear Creek Ranger District
States:
Colorado
Counties:
Clear Creek
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Nicole Malandri
101 Chicago Creek Road
Idaho Springs, CO 80452
303-567-3016
nicole.malandri@usda.gov
Last Updated: 8/16/2024