Intermountain Rural Electric (I-REA) Distribution Line
The Forest Services has made a decision to amend I-REA's permit to allow for a new 12.5 kv distribution line in the Squaw Pass area to connect the existing Blue Valley Electric Line to the Bergen Park Line.
Project Summary
Location Summary:
Squaw Pass Road
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/07/2011 |
| Comment Period | 03/29/2013 |
| Decision | 07/2013 (Estimated) |
| Implementation | 05/2014 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Clear Creek Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Floyd Hill Distribution Line Tie-In Project
Decision Signed Date: 07/09/2013
Legal Notice Date: 07/17/2013
Forests:
Arapaho and Roosevelt National Forests
Districts:
Clear Creek Ranger District
States:
Colorado
Counties:
Clear Creek
Legal Land Description:
6th PM, T4S, R72W, Section 20, 27, 28, 29
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Patti Turecek
101 Chicago Creek Road
Idaho Springs, CO 80452
303-567-3011
pturecek@fs.fed.us
Last Updated: 9/30/2013