Paving Weld County Road 105
Weld County is proposing to widen and pave the existing gravel Weld County Road (WCR) 105 from south of state highway (SH) 14 to WCR 390, approximately 4 miles. Approximately 3 miles of this proposed project crosses the Pawnee National Grassland.
Project Summary
Location Summary:
WCR 105 from south of SH 14 to WCR 390, approximately 4 miles.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 10/31/2016 |
| Comment Period | 12/05/2016 |
| Objection Period Start | 09/18/2017 |
| Decision | 11/2017 (Estimated) |
| Implementation | 11/2017 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Pawnee Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management; Road Management
Project Activity:
Special Use Authorizations; Road Improvements/Construction
Current Status:
Completed
Project Decision Information
Paving Weld County Road 105
Decision Signed Date: 11/21/2017
Forests:
Arapaho and Roosevelt National Forests
Districts:
Pawnee Ranger District
States:
Colorado
Counties:
Weld
Legal Land Description:
T.8 N. R. 60 W., Sixth PM, Sec. 2 W1/2, Sec.3,E1/2,Sec.10 E1/2, Sec. 11, W1/2, Sec. 14, W1/2, Sec. 15 E1/2, Sec. 22, E1/2, Sec.23 W1/2, Sec.27, NW 1/4.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Mary Chambers
P.O. Box 386
Ault , CO 80610
970 834 9288
machambers@fs.fed.us
Last Updated: 11/27/2017