Eldora Mountain Resort Electric Line Upgrade
The Forest Service proposes to authorize Eldora Mountain Resort to upgrade their electric line to support the Challenge Express ski lift which was approved in the Eldora Mountain Resort Ski Area Projects EIS decision in October 2015.
Project Summary
Location Summary:
The proposed new conduit is on skiers right (as the skier is heading downhill) on the edge of the Jolly Jug Ski Trail at Eldora Mountain Resort located near the town of Nederland.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/06/2017 |
| Decision | 06/2017 (Estimated) |
| Implementation | 06/2017 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Boulder Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission; Special Use Authorizations
Current Status:
Completed
Project Decision Information
Eldora Mountain Resort Electric Line Upgrade
Decision Signed Date: 06/09/2017
Forests:
Arapaho and Roosevelt National Forests
Districts:
Boulder Ranger District
States:
Colorado
Counties:
Boulder
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jaime Oliva
2140 Yarmouth Avenue
Boulder, CO 80301
303-541-2509
joliva@fs.fed.us
Last Updated: 7/19/2017