MPEI Hwy 125/NFSR 108.1 Install New Underground Electric and Rebuild Overhead Electric Service
Remove and replace electric transmission lines burned in the 2020 East Troublesome Fire and install underground vaults along three miles of Highway 125 and two miles along National Forest System Road 101.8.
Project Summary
Location Summary:
Junction of Hwy 125 and NFSR 108.1
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/05/2021 |
| Decision | 06/2021 (Estimated) |
| Implementation | 06/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Arapaho and Roosevelt National Forests All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
MPEI Hwy 125/NFSR 108.1 Install New Underground Electric and Rebuild Overhead Electric Service
Decision Signed Date: 06/24/2021
Forests:
Arapaho and Roosevelt National Forests
Districts:
Sulphur Ranger District
States:
Colorado
Counties:
Grand
Legal Land Description:
Sec. 1, 2, 3, 12 T4N R78W; Sec. 7, 18, 29 T4N R77W
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Shoshana Cooper
2150 Centre Avenue, Building E
Fort Collins, CO 80526
970-531-1646
shoshana.cooper@usda.gov
Last Updated: 6/24/2021