Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/09/2023 |
| Decision | 06/2024 (Estimated) |
| Implementation | 07/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Sulphur Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management
Project Activity:
Watershed Improvements
Current Status:
Completed
Project Decision Information
Willow Creek Avulsion
Decision Signed Date: 06/14/2024
Forests:
Arapaho and Roosevelt National Forests
Districts:
Sulphur Ranger District
States:
Colorado
Counties:
Grand
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Sarah Beck
9 Ten Mile Drive
Granby, CO 80446
970-692-3207
Sarah.Beck@usda.gov
Last Updated: 7/26/2024