United Power - Permit Renewal and Line Upgrade
The Forest Service Proposes to reauthorize continued use and operation of existing powerlines on Clear Creek and Boulder Ranger Districts. The Forest Service also proposes to allow upgrades to an existing line.
Project Summary
Location Summary:
Serves private inholdings and rural communities on BRD and CCRD; T2S, R73W, sec 25; T1S, R72W sec 28-34
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 05/04/2023 |
| Decision | 11/2023 (Estimated) |
| Implementation | 11/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3); 32.12 (11), 36 Cfr 220.6(D)(11)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Arapaho and Roosevelt National Forests All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
United Power - Permit Renewal and Line Upgrade
Decision Signed Date: 11/02/2023
Forests:
Arapaho and Roosevelt National Forests
Districts:
Boulder Ranger District; Clear Creek Ranger District
States:
Colorado
Counties:
Boulder; Clear Creek; Gilpin
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Leslie McFadden
2150 Centre Avenue, Building E
Fort Collins, CO 80526
970-295-6656
leslie.mcfadden@usda.gov
Last Updated: 2/8/2024