Xcel PSCo Gas Line Master Permit
PSCo seeks to renew their existing permits for natural gas transmission lines on the Forest. This will update expired/expiring authorizations and roll all current authorizations into one Forest master permit for the Utility's existing gas systems.
Project Summary
Location Summary:
This is a Forest-Wide permit renewal/authorization.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/11/2024 |
| Decision | 04/2025 (Estimated) |
| Implementation | 04/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (11), 36 Cfr 220.6(D)(11)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Arapaho and Roosevelt National Forests All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Xcel PSCo Gas Line Master Permit
Decision Signed Date: 04/03/2025
Forests:
Arapaho and Roosevelt National Forests
Districts:
Arapaho and Roosevelt National Forests All Units
States:
Colorado
Counties:
Boulder; Clear Creek; Gilpin; Grand; Jefferson; Larimer
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Nicole Malandri
2150 Centre Avenue, Building E
Fort Collins, CO 80526
303-567-3016
nicole.malandri@usda.gov