I-17 Hog Water Communication Site
Proposal to construct a new communication 140 foot tall tower, buildings and solar power system to improve wireless service along Interstate 17.
Project Summary
Location Summary:
Along I-17 and Forest Road 689 near an existing ADOT storage site and Rarrick Canyon.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/16/2018 |
Decision | 10/2018 (Estimated) |
Implementation | 11/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Red Rock Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
I-17 Hog Water Communication Site
Decision Signed Date: 10/29/2018
Forests:
Coconino National Forest
Districts:
Red Rock Ranger District
States:
Arizona
Counties:
Yavapai
Legal Land Description:
Section 35, T16 N., R6 E, G&SRM
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Judy Adams
8375 State Route 179
Sedona, AZ 86351
928-203-7506
jadams05@fs.fed.us
Last Updated: 11/2/2018