Fiber Optic Line Placement along North Highway 89
Placement of a fiber optic cable by Arcadian Infracom within the Hwy 89 right-of-way from Flagstaff to the Coconino NF northern boundary.
Project Summary
Location Summary:
Within Hwy 89 existing right-of-way from Flagstaff to Coconino NF northern boundary on the east side of the highway
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/14/2021 |
Decision | 06/2022 (Estimated) |
Implementation | 07/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Coconino National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Arcadian Infracom: Fiber Optic Line Placement Along North Highway 89Fiber O
Decision Signed Date: 06/17/2022
Forests:
Coconino National Forest
Districts:
Coconino National Forest All Units
States:
Arizona
Counties:
Coconino
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Sean Murphy
1824 S. Thompson St.
Flagstaff, AZ 86001
928-527-3418
sean.murphy@usda.gov