Sparklight Fiber Optic Line in Cornville Area
Sparklight proposes to hang fiber optic line along existing APS poles for approximately three miles in the Cornville area. The purpose of the fiber optic line would be to increase broadband infrastructure, particularly at area schools.
Project Summary
Location Summary:
Cornville area, including Beaverhead Flat Road
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/30/2022 |
Decision | 07/2022 (Estimated) |
Implementation | 07/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Red Rock Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Sparklight Fiber Optic Line in Cornville Area
Decision Signed Date: 07/15/2022
Forests:
Coconino National Forest
Districts:
Red Rock Ranger District
States:
Arizona
Counties:
Yavapai
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Elizabeth Munding
8375 State Route 179
Sedona, AZ 86351
928-203-2914
elizabeth.a.munding@usda.gov
Last Updated: 9/22/2022