Qwest Corp. D/B/A CenturyLink QC
Centurylink will install approx. 6400 feet of fiberoptic cable in existing conduit along Hwy 179 headed south to the Red Rock R.D. and splice fiberline into F.S. office. One concrete tele-comm pedestal adjacent to the office will be replaced.
Project Summary
Location Summary:
Beginning at Ridgeway Dr. and Hwy 179 in the Village of Oak Creek moving south along the Hwy 179 corridor ending at 8375 Hwy 179 (RedRock R.D. office)
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/06/2023 |
Decision | 05/2023 (Estimated) |
Implementation | 07/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Red Rock Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Qwest Corp. D/B/A CenturyLink QC
Decision Signed Date: 05/01/2023
Forests:
Coconino National Forest
Districts:
Red Rock Ranger District
States:
Arizona
Counties:
Yavapai
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Tobias Hutchens
8375 State Route 179
Sedona, AZ 86351
928-527-3471
tobias.j.hutchens@usda.gov