Tucson Electric Power Co. Enhancement of the Existing Communication Site on Fox Mountain
TEP proposes to replace the existing 20' microwave tower with a 120' tower. Along with this, two new antennas and communication radios will replace the existing equipment. The new tower will have a new concrete pad. The old equipment will be removed.
Project Summary
Location Summary:
Within the Fox Mountain Communication Site.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/15/2014 |
Decision | 07/2015 (Estimated) |
Implementation | 08/2015 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Gila National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Tucson Electric Power Co. Enhancement of the Existing Communication Site on Fox Mountain
Decision Signed Date: 07/06/2015
Forests:
Gila National Forest
Districts:
Quemado Ranger District
States:
New Mexico
Counties:
Catron
Legal Land Description:
NW1/4 NE1/4 NW1/4 Section 3, T.3 S., R.18 W., NMPM.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
John Baumberger
3005 E. Camino del Bosque
Silver City, NM 88061-7863
575-388-8238
jbaumberger@fs.fed.us
Last Updated: 6/29/2016