Sierra Electric Cooperative Powerline Reroute
Sierra Electric Cooperative, Inc. has applied to modify their permit to construct and operate 0.8 miles of re-routed segment of the powerline across NFS lands and upgrade the entire line to 14.4Kv. The old poles and lines would be removed.
Project Summary
Location Summary:
The powerline runs from Cuchillo Substation off forest and mostly parallels Hwy 59 on Forest. The re-route site is located approx. 1.5 miles east of Poverty Creek parallel to Hwy 59
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/22/2019 |
Decision | 02/2020 (Estimated) |
Implementation | 10/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Black Range Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Sierra Electric Cooperative Powerline Reroute
Decision Signed Date: 02/26/2020
Forests:
Gila National Forest
Districts:
Black Range Ranger District
States:
New Mexico
Counties:
Catron
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Michael Hutchins
1804 North Date Street
T or C, NM 87901
575-894-6677
michael.hutchins@usda.gov
Last Updated: 3/26/2020