Eastside Powerline Special Use Permit Renewal
Re-authorization of special use permits for existing electric transmission and distribution lines that have expired permits.
Project Summary
Location Summary:
Eastside of the Tahoe National Forest on the Sierraville and Truckee Ranger Districts
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/10/2012 |
Comment Period | 02/12/2014 |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (15)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Tahoe National Forest All Units
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Eastside Powerlines Special Use Permit Renewals
Decision Signed Date: 03/24/2014
Forests:
Tahoe National Forest
Districts:
Sierraville Ranger District; Truckee Ranger District
States:
California
Counties:
Nevada; Placer; Sierra; Yuba
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public