Cal-Ida Trail Connection EA
Construct new trail links to reduce accident risk by OHVs, etc. Will provide additional miles of single track trails to enhance current use of area.
Project Summary
Location Summary:
North of Hwy 49 off Cal-Ida Rd and parallel to Forest Road 25
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/04/2016 |
Comment Period | 09/07/2016 |
Objection Period Start | 10/06/2016 |
Decision | 12/2016 (Estimated) |
Implementation | 05/2017 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Yuba River Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Recreation Management
Project Activity:
Dispersed Recreation Mgmt.; Trail Management
Current Status:
Completed
Project Decision Information
Cal-Ida Trail Connection EA
Decision Signed Date: 12/06/2016
Forests:
Tahoe National Forest
Districts:
Yuba River Ranger District
States:
California
Counties:
Sierra
Legal Land Description:
T19,20,21N; R9,10E; Multiple Secs
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Paul Hart
15924 Highway 49
Camptonville, CA 95922
530-226-2337
pdhart@fs.fed.us
Last Updated: 12/8/2016