Tahoe-Truckee Sanitation Agency Interceptor Improvement Project
Replacement of 24-inch sewer line with 36-inch sewer line on existing Truckee River Interceptor alignment. Objective to increase line capacity to avoid system overload.
Project Summary
Location Summary:
xxxUSGS 7.5' Quad: Truckee, California (1992), T17N R16E Section 28 Mount Diablo Meridian.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/25/2016 |
Decision | 01/2017 (Estimated) |
Implementation | 05/2017 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Truckee Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Tahoe-Truckee Sanitation Agency Interceptor Improvement Project
Decision Signed Date: 01/03/2017
Forests:
Tahoe National Forest
Districts:
Truckee Ranger District
States:
California
Counties:
Placer
Legal Land Description:
USGS 7.5' Quad: Truckee, California (1992), T17N R16E Section 28 Mount Diablo Meridian.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Karie Wiltshire
10811 Stockrest Springs Road
Truckee, CA 96161
530-994-3401 x6680