APS 69kv Power Line Permit for Childs-Irving Line
Issuance of a permit to replace the expired Federal Energy Regulatory Commission Hydropower License. Existing 69 kV line that was part of the Childs Irving Power operation and covered under the old license. Has been in continuous operation.
Location Summary
Line that travels from Childs substation to Irving power plant area. Includes small sections of the Tonto NF where it crosses Fossil Creek.
Forests: Red Rock Ranger District, Payson Ranger District
Project Milestones
| Milestone | Date |
|---|---|
| Scoping Start | 08/12/2015 |
| Comment Period | N/A |
| Objection Period Start | N/A |
| Decision | 08/2023 (Estimated) |
| Implementation | 08/2023 (Estimated) |
Project Documents
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public