Bridger Pipeline, L.L.C. crude oil gathering pipeline proposals.
Two 8 inch steel crude oil gathering pipelines.One in Section 22, T148N, R98W, and one in Section 18, T148N, R100W, 5th PM, McKenzie County, North Dakota.
Project Summary
Location Summary:
12 air miles SE of Watford city, ND and 15 air miles South of Watford City, ND
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/31/2012 |
Comment Period | 08/31/2012 |
Decision | 09/2013 (Estimated) |
Implementation | 12/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Mckenzie Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Minerals And Geology; Special Use Management
Project Activity:
Oil
Current Status:
Completed
Project Decision Information
Decision Memo for Bridger Pipeline, LLC Crude Oil Gathering Pipeline
Decision Signed Date: 09/27/2013
Legal Notice Date: 10/02/2013
Forests:
Dakota Prairie Grasslands
Districts:
Mckenzie Ranger District
States:
North Dakota
Counties:
McKenzie
Legal Land Description:
Section 22, T148N, R98W, and Section 17, T148N, R100W, 5th PM, McKenzie county, ND
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kim Grotte
1905 Main St. South
Watford City, ND 58854-6705
701-842-2393
kgrotte@fs.fed.us