Roughrider Electric upgrade/intall overhead & Buried Electric Line
upgrade 7863 feet of overhead and install 614 feet of buried three phase electric line to connect Continental 1X-21H and 1-25H oil wells on private land
Project Summary
Location Summary:
28 miles north of Belfield, ND
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/29/2013 |
Comment Period | 01/30/2013 |
Decision | 07/2013 (Estimated) |
Implementation | 10/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Medora Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Roughrider Electric upgrade/intall overhead & Buried Electric Line
Decision Signed Date: 07/11/2013
Legal Notice Date: 07/11/2013
Forests:
Dakota Prairie Grasslands
Districts:
Medora Ranger District
States:
North Dakota
Counties:
Billings
Legal Land Description:
28-144-99
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Martina Thornton
99 23rd Avenue W, Suite B
Dickinson, ND 58601-3135
701-227-7809
mthornton@fs.fed.us
Last Updated: 9/30/2013